We have the production/supply ability that perfectly satisfies the needs with quality control.
01
Put sleeves which is fitting on an external diameter inside laid cable. Due to sleeve’s splitting, it is easy to put into it from the front side by hand.
02
Put filler sleeves as 19/27 or 12/18 at the empty space after putting sleeve inside laid cable.
03
Arrange already stuffed sleeve to make 20mm space on both sides.(Sealant should be filled in 20mm space with an error tolerance of 4mm)
04
Fill the sealant to 20mm empty space by sealant filler. Before fill the sealant, make sure that there is no oil or dust things and it is dry on the surface. (Dust/moisture/corrosion or oil stain could disturb adhesion)
05
When finish sealant, it can be pushed to empty inside a little.
So make it thick than cross section.
06
Prepare a soapy water soaked cloth to make sealant treated surface smooth and looking good. Press down sealant surface slightly.(Soak cloth in soapy water is for preventing sealant stick to cloth) (But soapy water just should be used in finishing because of adhesive strength deterioration)
07
For the crack between cables, put and press down sealant with thin and flat tool.
It is for air and water proofing.